Our Projects

Mare Harbour - East Cove, The Falklands 
Mobilisation of 5000 tonne of plant and equipment from Moerdijk Holland, including 350t, 160t and 90t crawler cranes.
 
The largest demountable jack up barge with deck capacity of 800 tonne. Demountable multicat vessel and 60m x 20m supply barge.
 
Project comprised of pre-drilling 13no 3mx20m below sea bed into existing sandstone.  Installation and in situ grouting of 10no 80t birthing piles and 3no mooring piles connected by 130m of on site assembled Mabey panel bridge.
 
Intstallation of 10no 30t Trelleberg super cone fenders.
 
Replacement of existing fire pump and pipe work.  Concrete repairs to existing caisson dolphins and replacement of edge protection.
 
Assembly and installation of new Versadock small boat pontoon.

 

 